Project Gantt Chart for Job Cash Flow Management

Project Gantt Chart for Timed Forecasting Grid

Anterra’s vision for construction BI is focused on job forecasting.  In order to forecast job cash flow, project dates must be centrally managed. Most companies do not update project start and end dates in their accounting systems. Project managers typically are not given access to the job setup where the date fields are located. Anterra’s solution to cash flow forecasting and job control is to provide a central Gantt chart to:

  1.  Set project start and end dates
  2. Change project start and end dates (requiring the cost of a date change be identified)
  3. Show a log of all date changes
  4. Shows all active projects
  5. Provides an overview of project timing by company, division, and project manager
The Gantt chart component is under the Construction menu:

Please contact Anterra if you would like to test the Gantt Chart – we will need to turn off the updating of project dates from your accounting system.

The Project Gantt Chart shows all active jobs:


Clicking on a project name opens the date management pop up:

date management pop up























As you fill in the date change are asked for the reason for the change in dates:
                    reason
You can maintain this list in the Admin > UI Administration > Action Item Administration where we added the project date change reason as a managed field.  You can edit existing reasons, add, delete and order items. Edit the start and end dates as required, the total project duration is displayed before and after you change dates:

             action item admin

Enter the cost of the change and if it is fully recoverable, partially recoverable or not, and a note.  If you select fully or partially recoverable you are asked to enter the claimed amounts and the CO Number:

change order number

To see a log of project date changes click on the Project End Date on the Gantt Chart:

project end date

date change log














    • Related Articles

    • Anterra Version v25.2 Release Notes

      Anterra Version 25.2 Release Notes Updates to Anterra Pivot Grids These are general updates that apply to most of the grids through every module (Finance, Construction, and Service Management) Setting the Default Date for a Pivot Grid - KB Pivot ...
    • Job Forecasting at the Cost Category level

      Start at the Job To enter a forecast, first launch the Project Cost Scorecard report. Once the report loads, select the job you want to build a forecast for by drilling down on either the Job to Date cost or the JTD Forecast at Complete number for ...
    • Gantt Chart

      Overview What is the Gantt chart used for? Gantt charts help teams to plan work around deadlines and properly allocate resources. A Gantt chart is a commonly used graphical depiction of a project schedule. It's a type of bar chart showing the start ...
    • Reasons Why Projects Are Not Visible on the Final Margin Grid

      Only closed projects with an actual completion date will appear on the Final Margin Grid. The reason for this restriction is because of how the date parameters on the top of the grid filter to jobs within a range of completion dates as shown below:   ...
    • Job Forecasting Hub Training

      What is it? The 'Job Forecasting Hub' is the name of the first place you go in Anterra to begin adjusting the forecast cost at complete for your projects. The Anterra Platform shows the current values for the forecasts but stores the changes to the ...